Heap leach column scale-up calculator

Enter the column size, bulk density, application rate and days leached. The calculator gives the solution to ore ratio reached and the days a heap lift of your height needs for the same ratio.

Results

The example values are filled in so you can see how it works. Results update as you type.

The formula

q=QARs/o=∑VappliedMtheap=Rs/o×H×ρbq

where

q
application rate: solution per hour per square metre of surface (L/h·m²)
Q, A
solution flow (L/h) and irrigated area (m²)
Rs/o
solution to ore ratio: total solution applied per tonne of ore (m³/t, the same as L/kg)
M
dry ore mass (t)
theap
time a heap needs to receive the same ratio (h; divide by 24 for days), with the rate in m³/h·m²
H, ρb
lift height (m) and bulk density of the stacked ore (t/m³)

Want the background? Read Heap leach column tests: procedure, solution-to-ore ratio and scale-up to the heap.

Discuss your plant with a metallurgist

Tiegel is a Perth metallurgy company. We help with testwork, plant optimisation, metal accounting and investigations.

Talk to a metallurgist

These calculators use standard published formulas and are provided as a guide. Check results before relying on them for design or reporting.